New Middle School Construction Progress

Ground Water Monitoring

Ground Water Monitoring

Installation of ground water monitoring piezometers (An instrument used for measuring the pressure of a liquid or gas. Piezometers are often placed in boreholes to monitor the pressure or depth of groundwater.) on the new Middle School Site. Along with the analysis of...

And So It Begins…

And So It Begins…

By now, you have heard that the Bond to build a new La Center Middle School passed with nearly 66% of the vote--thank you again to all who partipated! Now the real work begins! This blog will be used to keep YOU, the parents, students and community of La Center up to...

MAJOR STAGES of SCHOOL CONSTRUCTION

Bond PassageCOMPLETED

Architecture Firm SelectionCOMPLETED

Educational Specifications COMPLETED

Schematic Design COMPLETED

Design Development COMPLETED

Construction Documents COMPLETED

Secure all necessary permitsFINALIZING

Contractor Bids and NegotitationsCOMPLETED

Construction – Will Begin in early Spring, 2020

Occupancy